Anhui power system Abendkleid held a 500,000 volt channel ACC

Ben on June 5, 500,000 volts of Anhui power grid construction channel transmission project in the East, ACC held in Hefei.
Deputy Liu Bo, Chief Engineer of Anhui Province electric power company, infrastructure Director Chang Xianmi attended, Deputy General Manager of Anhui power transmission and transformation engineering company Zhu Keliang and along the city power supply companies, management companies, electric power Design Institute unit responsible person present at the meeting. Meeting chaired by the company infrastructure Department of Anhui Province.
500,000 volts of Anhui power grid in the channel–fertilizer ⅱ back to the line of the new single loop and 500,000 volts, and Los fertilizer to transform on double-circuit in two parts, the new single loop 105.5 km, 3.5 km double circuit, total 274 base iron Tower. Ongoing Foundation construction, based cast-94 base were completed as at the end of May. 500,000 volt East passage includes the line 2×239.5+123km, huaihe River long span 2+2.56km, 2 new substation, extension 3 substation (station), specifically:
500 kilovolt substation project: new 500-Huai, Bengbu, install 1×75 of thousands kVA transformer, extension 3 interval of chuzhou, extension 2 interval of chaohu Lake, Ma On Shan station extension;
500,000-volt lines project: Suzhou power plant to Huai 2×18 of double lines km; Huai host variable to Bengbu and 2×130.5 km of double lines; the huaihe River long span 2×2.45 km; Bengbu to to chuzhou to 2×91 km of double lines; chuzhou-chaohu-long span ⅱ back to Ma On Shan line, single circuit line 123 Cocktailkleider km. East
500 kV channel project began in May 2006 and is planned to be completed in June 2007.
construction units and building on, namely project profile and project construction progress, there is a problem and plan to conduct a report on the next statement. Province company infrastructure Department on East, and in the channel lose variable electric engineering of land, and planning, and construction figure, and material supply, problem for has full coordination, pointed out that 2006 is Anhui grid construction of key a years, all parameter built units to further seek unity, height awareness Anhui grid 500,000 v East, and in the channel construction of importance, full implementation province company 2006 infrastructure working conference spirit, close combined with, strengthening responsibility, obey and service Yu engineering construction, timely coordination processing good appears of contradictions and problem, Correctly handle the relationship of each aspect to ensure channel transmission project completed in the East, putting into operation. (Fan Yazhou, and Wang Longsheng)